Block work is complete up to the 9th floor and is progressing from the 10th to the top floor.

Plastering has been completed up to the 6th floor and is progressing up to 12th floor.

Curtain wall work is ongoing.

The contractor has issued the revised drawings for the common areas after addressing The First Group interior’s design team earlier comments. These drawings are under review by The First Group’s Interior design team pending their final approval.

The First Group’s interior design team has submitted the final detailed design drawings of the F&B outlets to the operator for their review.