The First Collection At Dubai Sports City

Introducing The First Collection at Dubai Sports City, the newest addition to our award-winning The First Collection portfolio. This urban retreat features 488 well-appointed guestrooms and suites, top-tier amenities, outstanding leisure facilities, and three signature dining outlets. The First Collection at Dubai Sports City offers a chance to experience Dubai’s leading sport-focused community, conveniently located near Dubai’s major business sectors and renowned leisure destinations.

Dubai Sports City stands as the vibrant, cosmopolitan hub of New Dubai. As the world’s premier sports-lifestyle community, it houses exceptional facilities such as an international cricket stadium, championship golf course, professional sports academies, and a vast array of retail and lifestyle venues.

Nestled in the heart of this bustling centre, The First Collection at Dubai Sports City carries forward the values of our esteemed hotel brand, ensuring unforgettable and exceptional moments for both business and leisure guests.

FACILITIES

24 Hours Reception

24 Hours Reception

24 hours reception

Valet Parking

Valet Parking

Valet parking

Business Lounge

Business Lounge

Business Lounge

Laundry Service

Laundry Service

Laundry Service

High-Speed Wi-Fi

High-Speed Wi-Fi

Wi-Fi

World-Class Dining

World-Class Dining

World-Class Dining

Swimming Pool

Swimming Pool

Swimming Pool

Fitness Centre

Fitness Centre

Fitness Centre

Streaming Services

Streaming Services

Streaming Services

Booking Facilities

Booking Facilities

Beach Club Access

Progress Updates

February 2026 - March 2026 Updates:

• Superstructure works are complete.

• Blockwork is in progress and has reached the 21st Floor.

• Plastering activities are in progress and have reached the 19th Floor.

• Dry area tile works are in progress and have reached the 6th Floor

• MEP works are in progress throughout the building, with 45% completed.

• Curtain wall installation is in progress, with 12% completed.

• Main contractor overall progress has reached 48% completion.

• The hotel guest room mock-up is complete, with enhancements in progress based on operator feedback.

• Mock-up works for the typical lift lobby and corridor are in progress.

• The latest Dubai Land Department report indicates overall progress at 40.07%.