December 2023 - January 2024 Updates:

The fit-out contractor has completed 20% of the installation work at the all-day dining area.

The First Group Interior Design team is working with the hotel operator to finalise the theme for the VIP guestrooms.

The appointed contractor for the leisure deck at level 01 has completed 10% of the work.

The appointed fit-out contractor for the main lobby has commenced work.

The First Group project team and the project consultant are obtaining approval from authorities for changes to the BOH area, as per the operator's request to enhance circulation and services.

The contractor is prepping the surface for carpet installation at the typical corridor level.