31st floor slab (26th guestroom floor) was cast on 24/08/19.

32nd floor slab (27th restaurant floor) will be cast on 10/09/19.

The roof slab (final slab) will be cast on 30/09/2019. This will be the completion of the super structure of the building.

Block work is in progress up to the 28th typical floor.

Plaster work is in progress up to the 15th typical floor.

Curtain wall work is ongoing.

The First Group’s interior design team has submitted the final detailed design drawings of the F&B outlets and the corridors to the operator for their review.

The First Group’s interior design team has issued the revised drawings for the various front and back of house areas after addressing the operator’s earlier comments.