More Information

December 2023 - January 2024 Updates:

The project consultant, operator, and contractor are completing the snag list.

The MEP contractor is attending to comments from the Fire, Life, and Safety (FLS) audit.

The furniture contractor has commenced with fabrication of the guestroom furniture.

Fit-out work for the GF main lobby, public bathroom, and lift lobby is 70% complete.

Fit-out work for the gym, spa, and public bathroom at level 5 is 75% complete.

The First Group Interior Design team is developing the design for the typical corridor level.

The project consultant and operator are conducting third-party testing for the building services, including the lifts and Building Maintenance Unit (BMU).

The project consultant is conducting tests and the commissioning of the building façade lighting system.