Construction Status
January 2012
PHASE TWO:
Building 7, 8, 9
- Power and water have been provided to the 3 buildings.
- Tenants have moved into buildings 7, 8 & 9.
Building 10

Building 11

PHASE THREE:
Building 12
- Central Lake:
All waterproofing membrane work is complete. Stone work to the water feature bank is 95% and Uniestate are aiming for completion by the end of January 2012. - Perimeter Fence:
The perimeter fence has been completed up to the site boundary of the Phase 2 works. The next phase will not be completed until completion of Phase 2 and the removal of site facilities. The site has been cleaned of rubble and a temporary hoarding has been constructed preventing access from the recently completed buildings 7, 8 & 9 and the buildings still under construction.

General Area
* Please note that the details of construction progress for this development are largely provided to us by the project consultants and contractors. Any reference to future construction milestone dates is in accordance with their reports to us and The First Group are unable to accept responsibility for any errors.