Journey To Ras Al Khaimah
Click to view the Virtual Helicopter Tour of RAK, piloted by Michael Owen.
Platinum Dubai Experience
See Dubai in Style – take advantage of our exclusive Property Tour
Find out more
In order to view this site in full please upgrade your version of the flash player.
Construction Status
March Report
PHASE ONE:
- Buildings 1, 2, 3, 4, 5 & 6 de snagging has been completed.
- The asphalt roads now reach to building 6.
- The excavation for the lake has been completed from building 1 side up to Building 8.
- The tender for the MEP and civil works related to lake have been floated to the contractors.
PHASE TWO:
- The super structure concrete works for all the buildings are complete.
- Block work in Buildings 10 & 11 has been completed.
- 90% of the wall's plaster works have been completed on buildings 11 and 100% on building 10.
- 85% of the wall's plaster works are completed for building 7, 8 & 9.
- Tile and paint's works have started in building 10 & 11.
- The block works are complete in buildings 7, 8 & 9.
* Please note that the details of construction progress for this development are largely provided to us by the project consultants and contractors. Any reference to future construction milestone dates is in accordance with their reports to us and The First Group are unable to accept responsibility for any errors.


