Construction History

March 2012

PHASE TWO:

Building 7, 8, 9

  • Power and water have been provided to the 3 buildings.
  • Tenants have moved into many of the units in buildings 7, 8 & 9.

Building 10

Yasmin Village

Building 11

Yasmin Village

PHASE THREE:

Building 12

    Yasmin Village

    General Area

    • Central Lake:
      All waterproofing membrane work is complete. Stone work to the water feature bank is 100% complete and it is planned to fill it with water by the middle of April 2012.
    • Perimeter Fence:
      The perimeter fence has been completed up to the site boundary of the Phase 2 works. The next phase of fencing will be completed after the full completion of Phase 2 and the removal of construction related equipment. The site has been cleaned of rubble and a temporary hoarding has been constructed preventing access from the recently completed buildings 7, 8 & 9 and the buildings still under construction.

    February 2012

    PHASE TWO:

    Building 7, 8, 9

    • Power and water have been provided to the 3 buildings.
    • Tenants have moved into many of the units in buildings 7, 8 & 9.

    Building 10

    Yasmin Village

    Building 11

    Yasmin Village

    PHASE THREE:

    Building 12

      Yasmin Village

      General Area

      • Central Lake:
        All waterproofing membrane work is complete. Stone work to the water feature bank is 100% complete and it is planned to fill it with water by the middle of April 2012.
      • Perimeter Fence:
        The perimeter fence has been completed up to the site boundary of the Phase 2 works. The next phase of fencing will be completed after the full completion of Phase 2 and the removal of site facilities. The site has been cleaned of rubble and a temporary hoarding has been constructed preventing access from the recently completed buildings 7, 8 & 9 and the buildings still under construction.

      January 2012

      PHASE TWO:

      Building 7, 8, 9

      • Power and water have been provided to the 3 buildings.
      • Tenants have moved into buildings 7, 8 & 9.

      Building 10

      Yasmin Village

      Building 11

      Yasmin Village

      PHASE THREE:

      Building 12

        Yasmin Village

        General Area

        • Central Lake:
          All waterproofing membrane work is complete. Stone work to the water feature bank is 95% and Uniestate are aiming for completion by the end of January 2012.
        • Perimeter Fence:
          The perimeter fence has been completed up to the site boundary of the Phase 2 works. The next phase will not be completed until completion of Phase 2 and the removal of site facilities. The site has been cleaned of rubble and a temporary hoarding has been constructed preventing access from the recently completed buildings 7, 8 & 9 and the buildings still under construction.

        December 2011

        PHASE TWO:

        Building 7, 8, 9

        • Power and water have been provided to the 3 buildings.
        • Tenants have moved in building 8& 9 and will soon move into building 7.

        Building 10

        Yasmin Village

        Building 11

        Yasmin Village

        PHASE THREE:

        Building 12

          Yasmin Village

          General Area

          • Central Lake:
            All waterproofing membrane work is complete. Stone work to the water feature bank is 95% and Uniestate are aiming for completion in January 2012.
          • Perimeter Fence:
            The perimeter fence has been completed up to the site boundary of the Phase 2 works. The next phase will not be completed until completion of Phase 2 and the removal of Site Facilities. The site has been cleaned of rubble and a temporary hoarding has been constructed preventing access from the recently completed Buildings 7, 8 & 9 and the Buildings still under construction.

          November 2011

          PHASE TWO:

          Building 7, 8, 9

          • The completion certificates for the 3 buildings have been issued by RAK municipality. That means that the buildings are ready for occupancy.

          Building 10

          Yasmin Village

          Building 11

          Yasmin Village

          PHASE THREE:

          Building 12

            Yasmin Village

            General Area

            • The lake area: major civil works are completed and 95% of the waterproofing membrane is complete.
            • Road infrastructure is ongoing.

            October 2011

            PHASE TWO:

            Building 7, 8, 9

            • All units in the buildings were snagged inspected and approved by the consultant.
            • Civil defence final inspection was completed on 17/10/2011 and approval was granted.

            Building 10

            Yasmin Village

            Building 11

            Yasmin Village

            PHASE THREE:

            Building 12

              Yasmin Village

            September 2011

            PHASE TWO:

            Building 7, 8, 9

            • The buildings are ready and completed from construction point of view. The contractor has attended to all snags.
            • A completion certificate must be obtained from the municipality before the buildings can be occupied; the following inspections must first take place with the necessary approvals secured before the completion certificate can be issued.
            • Etisalat: Inspection complete and approval obtained.
            • Drainage: Inspection complete and approval obtained.
            • Civil defence: First inspection completed on 19/09/2011 and a second is expected on the 27/9/201. Approval is anticipated following this inspection.

            Building 10

            Yasmin Village

            Building 11

            Yasmin Village

            PHASE THREE:

            Building 12

              Yasmin Village

              Yasmin Village General Area

              • The lake area: Major civil works are completed and 95% of the waterproofing membrane is complete.
              • Projected completion is December 2011.
              • Perimeter fencing is completed in line with the staging of the development
              • Road infrastructure is ongoing.

              August 2011

              PHASE TWO:

              Building 7, 8, 9

              • Ground and Common Areas are due for 1st inspection on 25/08/2011.
              • Completed first snagging inspection of floors 1 – 4 of all 3 buildings
              • De-snagging in process in preparation for 2nd inspections over the next 10 days
              • Testing and commissioning of plant and equipment in final process and due for completion in next 10 – 15 days
              • Handover commences mid-September

              Building 10

              Yasmin Village

              Building 11

              Yasmin Village

              PHASE THREE:

              Building 12

              • Second storey slab formwork is set up and 50% cast with columns set for third storey slab.
              • Yasmin Village General Area

                • The lake area major civil works are completed and 95% of the waterproofing membrane is installed.
                • Projected completion date for lake is December 2011.
                • Perimeter fencing is completed in line with the staging of the development
                • Landscaping and pavement works underway
                • Road infrastructure is ongoing and in place into Phase 2.

              July 2011

              PHASE TWO:

              Building 7

              • Levels 1 & 2 initial snagging and handover inspections completed;
              • De snagging predominantly minor door scratches and chipped floor tiles;
              • Rectification to occur within one week for reinspection;
              • Initial snagging and handover on Levels 3 and 4 due for inspection 31 July;
              • Common areas and ground floor inspections scheduled for 14 August;
              • Second inspections following de snagging on all levels is scheduled between 25th- 31st August.

              Building 8

              • Levels 1 & 2 initial snagging and handover inspections completed
              • Initial snagging on Levels 3 & 4 due for inspection 2nd August;
              • Common areas and ground floor inspections scheduled for 16th August;
              • Second inspections following de snagging on all levels is scheduled between 25th- 31st August.

              Building 9

              • Levels 1 & 2 initial snagging due for inspection 7th August
              • Initial snagging on Levels 3 & 4 due for inspection 11th August;
              • Common areas and ground inspections scheduled for 18th August
              • Second inspections following de snagging on all levels is scheduled between 25th- 31st August.

              Building 10

              Yasmin Village

              Building 11

              Yasmin Village

              PHASE THREE:

              Building 12

              • 1st storey slabs are cast and stripped;
              • Half of the 2nd storey columns are cast expecting the formwork of the second half by end of July;

              June 2011 Report

              PHASE TWO:

              Buildings 7,8 & 9

              • 100% of all plastering work is complete.
              • 90% of all MEP works (electrical, mechanical, drainage, firefighting and water supply) are complete.
              • Wall tiling is in progress with average of 90% completed.
              • Painting works in progress with average of 80% completed.
              • Kitchen cabinets works: 94% completed.
              • Aluminum and metal work: 97% completed.

              Building 10

              • 70% of all carpentry & joinery works are complete.
              • 78% of Aluminum and metal works are complete.
              • 80% of all MEP works (electrical, mechanical, drainage, and water supply) are now complete.
              • Painting: 70% completed.
              • Wall tilling: 97%.
              • Floor tiling: 25%.

              Buildings 11

              • 84% of all plastering work is complete.
              • 75% of wall tiling is complete.
              • 77% of all MEP works by way of electrical, mechanical, drainage, and water supply works are now complete.
              • 34% of all carpentry & joinery works are complete.
              • Painting: 27% is completed.

              PHASE THREE:

              Building 12

              • Neck columns works are100% completed.
              • Solid blocks works under Tie beams are 100% completed.
              • Water proofing for footing and solid blocks are 100% completed.
              • Tie beams steel and shutter works are 100% completed.
              • Tie beams' water proofing is 100% completed.
              • Ground slab has been casted.
              • 1st slab casting has been done.
              • Neck columns works for the 2nd floor slab are in progress.

              May 2011 Report

              PHASE TWO:

              Buildings 7,8 & 9

              • 100% of the sub-structure is complete.
              • 100% of super-structure is complete.
              • 100% of all block work is complete
              • 100% of all plastering work is complete.
              • 95% of the aluminium and metal work is complete.
              • 90% of kitchen cabinet installation is complete
              • 85% of all MEP works (electrical, mechanical, drainage, firefighting and water supply) are complete.
              • Painting works in progress with average of 70% completed.
              • Wall tiling is in progress with average of 85% complete.

              Building 10

              • 100% of the sub-structure is complete.
              • 100% of super-structure is complete.
              • 100% of all block work is complete
              • 97% of wall tiling is complete.
              • 77% of all MEP works (electrical, mechanical, drainage, and water supply) are now complete.
              • 75% of Aluminum and metal works are complete.
              • 60% of all carpentry & joinery works are complete.
              • 65% of interior paintwork is complete.
              • Floor tiling is 18% complete.

              Buildings 11

              • 100% of the sub-structure is complete.
              • 100% of super-structure is complete.
              • 100% of all block work is complete.
              • 80% of all plastering work is complete
              • 70% of wall tiling is complete.
              • 70% of all MEP works by way of electrical, mechanical, drainage, and water supply works are now complete.
              • 30% of all carpentry & joinery works are complete.
              • 23% of interior paintwork is complete .

              PHASE THREE:

              Building 12

              • Neck column work is 100% completed.
              • Solid block work under Tie beams is 100% completed.
              • Water proofing for footing and solid blocks are 100% completed.
              • Tie beams steel and shutter works are 100% completed.
              • Tie beams' water proofing is 100% completed.
              • Grade slab is completed.
              • Steel works for columns for 1st floor are in progress.

              April 2011 Report

              PHASE TWO:

              Buildings 7,8 & 9

              • 100% of the sub-structure is complete.
              • 100% of super-structure is complete.
              • 100% of all block work is complete
              • 100% of all plastering work is complete.
              • 70% of the aluminium and metal work is complete.
              • 60% of kitchen cabinet installation is complete
              • 55% of all MEP works (electrical, mechanical, drainage, firefighting and water supply) are complete.
              • Painting works in progress with average of 45% completed.
              • Wall tiling is in progress with average of 70% complete.

              Building 10

              • 100% of the sub-structure is complete.
              • 100% of super-structure is complete.
              • 100% of all block work is complete
              • 97% of wall tiling is complete.
              • 74% of all MEP works (electrical, mechanical, drainage, and water supply) are now complete.
              • 70% of Aluminum and metal works are complete.
              • 55% of all carpentry & joinery works are complete.
              • 60% of interior paintwork is complete.
              • Floor tiling is 18% completee.

              Buildings 11

              • 100% of the sub-structure is complete.
              • 100% of super-structure is complete.
              • 100% of all block work is complete.
              • 80% of all plastering work is complete
              • 68% of wall tiling is complete.
              • 65% of all MEP works by way of electrical, mechanical, drainage, and water supply works are now complete.
              • 25% of all carpentry & joinery works are complete.
              • 20% of interior paintwork is complete.

              PHASE THREE:

              Building 12

              • Neck column work is 100% completed.
              • Solid block work under Tie beams is 100% completed.
              • Water proofing for footing and solid blocks are 100% completed.
              • Tie beams steel and shutter works are 100% completed.
              • Tie beams' water proofing is 100% completed.
              • Grade slab 97% completed.
              • Steel works for columns at the ground floor is 75% completed.
              • Column/core wall casting for the ground floor is 50% completed.

              March 2011 Report

              PHASE TWO:

              Buildings 7,8 & 9

              • 100% of the sub-structure is complete.
              • 100% of super-structure is complete.
              • 100% of all block work is complete.
              • 98% of all plastering work is complete.
              • 65% of the aluminium and metal work is complete.
              • 55% of kitchen cabinet installation is complete.
              • 55% of all MEP works (electrical, mechanical, drainage, firefighting and water supply) are complete.
              • Painting works in progress with average of 45% completed.
              • Wall tiling is in progress with average of 70% complete.

              Building 10

              • 100% of the sub-structure is complete.
              • 100% of super-structure is complete.
              • 100% of all block work is complete.
              • 97% of wall tiling is complete.
              • 70% of all MEP works (electrical, mechanical, drainage, and water supply) are now complete.
              • 70% of Aluminum and metal works are complete.
              • 70% of all MEP works (electrical, mechanical, drainage, and water supply) are now complete.
              • 55% of all carpentry & joinery works are complete.
              • 60% of interior paintwork is complete.
              • Wall tiling is 97% complete.
              • Floor tiling is 15% complete.

              Buildings 11

              • 100% of the sub-structure is complete.
              • 100% of super-structure is complete.
              • 100% of all block work is complete. 80% of all plastering work is complete.
              • 68% of wall tiling is complete.
              • 60% of all MEP works by way of electrical, mechanical, drainage, and water supply works are now complete.
              • 25% of all carpentry & joinery works are complete.
              • 20% of interior paintwork is complete.

              PHASE THREE:

              Building 12

              • Neck column work is100% completed.
              • Solid block work under Tie beams is 100% completed.
              • Water proofing for footing and solid blocks are 100% completed.
              • Tie beams steel and shutter works are 100% completed.
              • Tie beams water proofing is 100% completed.
              • Grade slab 97% completed.
              • Steel works for columns at the ground floor is 75% completed.
              • Column/core wall casting for the ground floor is 50% completed.

              February 2011 Report

              PHASE TWO:

              Buildings 7,8 & 9

              • 100% of the sub-structure is complete.
              • 100% of super-structure is complete.
              • 100% of all block work is complete.
              • 98% of all plastering work is complete.
              • 50% of kitchen cabinet installation is complete.
              • 48% of all MEP works (electrical, mechanical, drainage, firefighting and water supply) are complete.
              • 50% of the aluminium and metal work is complete.
              • Painting work is in progress with average of 35% completion.
              • Wall tiling is in progress with average of 35% completion.

              Building 10

              • 100% of the sub-structure is complete.
              • 100% of super-structure is complete.
              • 100% of all block work is complete
              • 97% of wall tiling is complete.
              • 66% of all MEP works (electrical, mechanical, drainage, and water supply) are now complete.
              • 64% of Aluminum and metal works are complete.
              • 60% of interior paintwork is complete.
              • 55% of all carpentry & joinery works are complete.
              • Floor tiling is 12% complete.

              Buildings 11

              • 100% of the sub-structure is complete.
              • 100% of super-structure is complete.
              • 100% of all block work is complete.
              • 80% of all plastering work is complete.
              • 64% of wall tiling is complete.
              • 57% of all MEP works by way of electrical, mechanical, drainage, and water supply works are now complete.
              • 18% of all carpentry & joinery works are complete.
              • 15% of interior paintwork is complete.

              PHASE THREE:

              Building 12

              • Neck column works are 100% completed.
              • Solid block work under Tie beams is 100% complete.
              • Water proofing for footing and solid blocks are 100% completed.
              • Tie beams steel and shutter works are 100% completed.
              • Water proofing of Tie beams is 100% complete.
              • Grade slab is 75% completed.
              • Steel works for columns at the ground floor are 25% completed.

              January 2011 Report

              PHASE TWO:

              Buildings 7,8 & 9

              • 100% of the sub-structure is complete.
              • 100% of super-structure is complete.
              • 100% of all block work is complete.
              • 95% of all plastering work is complete.
              • 50% of kitchen cabinet installation is complete.
              • 45% of all MEP works (electrical, mechanical, drainage, firefighting and water supply) are complete.
              • 45% of the aluminium and metal work is complete.
              • Painting work is in progress with average of 30% completion.
              • Wall tiling is in progress with average of 25% completion

              Building 10

              • 100% of the sub-structure is complete.
              • 100% of super-structure is complete.
              • 100% of all block work is complete.
              • 97% of wall tiling is complete.
              • 61% of all MEP works (electrical, mechanical, drainage, and water supply) are now complete.
              • 60% of Aluminum and metal works are complete.
              • 60% of interior paintwork is complete.
              • 57% of the interior paintwork is complete.
              • 50% of all carpentry & joinery works are complete.
              • Floor tiling is 8% complete.

              Building 11

              • 100% of the sub-structure is complete.
              • 100% of super-structure is complete.
              • 100% of all block work is complete.
              • 75% of all plastering work is complete.
              • 60% of wall tiling is complete.
              • 53% of all MEP works by way of electrical, mechanical, drainage, and water supply works are now complete.
              • 10% of all carpentry & joinery works are complete.
              • 10% of interior paintwork is complete.

              PHASE THREE:

              Building 12

              • The back filling around and in between the foundations was completed.
              • 100% of water proofing for the footings and solid block under the tie beams has been completed
              • The contractor has started the steel and shutter work preparation for the Ground floor tie beams with 50% completed.

              December 2010 Report

              PHASE TWO:

              Buildings 7,8 & 9

              • 100% of the sub-structure is complete.
              • 100% of super-structure is complete.
              • 100% of all block work is complete.
              • 90% of all plastering work is complete.
              • 40% of all MEP works by way of electrical, mechanical, drainage, firefighting and water supply works are complete.

              Building 10

              • 100% of the sub-structure is complete.
              • 100% of super-structure is complete.
              • 100% of all block work is complete
              • 97% of wall tiling is complete.
              • 57% of the interior paintwork is complete.
              • 48% of all carpentry & joinery works are complete.
              • 42% of Aluminium and metal works are complete.
              • 58% of all MEP works by way of electrical, mechanical, drainage, and water supply works are now complete.

              Building 11

              • 100% of the sub-structure is complete.
              • 100% of super-structure is complete.
              • 100% of all block work is complete.
              • 72% of all plastering work is complete.
              • 55% of wall tiling is complete.
              • 50% of all MEP works by way of electrical, mechanical, drainage, and water supply works are now complete.

              PHASE THREE:

              Building 12

              • The back filling around and in between the foundations has been completed.
              • The contractor has started the steel and shutter works preparation for the Ground floor slab casting
              • Ground floor slab is due to be cast by end of December

              November 2010 Report

              PHASE TWO:

              Buildings 7,8 & 9 These 3 buildings are progressing in close parallel as follows:

              • These 3 buildings are progressing in close parallel as follows:
              • 100% of the sub-structure is complete.
              • 100% of super-structure is complete.
              • 100% of all block work is complete.
              • 87% of all plastering work is complete.
              • 37% of all MEP works by way of electrical, mechanical, drainage, firefighting and water supply works are now complete.

              Building 10

              • 100% of the sub-structure is complete.
              • 100% of super-structure is complete.
              • 100% of all block work is complete.
              • 96% of wall tiling is complete.
              • 53% of the interior paintwork is complete.
              • 40% of all carpentry & joinery works are complete
              • Aluminum and metal works 40% completed.
              • 53% of all MEP works by way of electrical, mechanical, drainage, and water supply works are now complete.

              Building 11

              • 100% of the sub-structure is complete.
              • 100% of super-structure is complete.
              • 100% of all block work is complete.
              • 69% of all plastering work is complete.
              • 52% of wall tiling is complete.
              • 45% of all MEP works by way of electrical, mechanical, drainage, and water supply works are now complete.

              PHASE THREE:

              Building 12

              • The foundations were cast on 29/9/2010.
              • The contractor has completed the tie beams for the foundation and is presently working on the columns.
              • The contractor has started the steel and shutter work preparation for the Ground floor slab casting which is expected to be towards the end of this month.

              October 2010 Report

              PHASE ONE:

              • Phase one buildings have been handed over.
              • Minor snags are being cleared by the contractor in the areas surrounding the buildings and inside a few units.
              • Approximately 55% of all apartments are now tenanted.

              PHASE TWO:

              Buildings 7,8 & 9 These 3 buildings are progressing in close parallel as follows:

              • These 3 buildings are progressing in close parallel as follows: 100% of the sub-structure is complete.
              • 100% of super-structure is complete.
              • 100% of all block work is complete.
              • 85% of all plastering work is complete
              • 35% of all MEP works by way of electrical, mechanical, drainage, firefighting and water supply works are now complete.

              Building 10

              • 100% of the sub-structure is complete.
              • 100% of super-structure is complete.
              • 100% of all block work is complete.
              • 95% of wall tiling is complete.
              • 90% of all plastering work is complete.
              • 70% of aluminium and glass works for the windows and doors is complete.
              • 50% of the interior paintwork is complete.
              • 49% of all MEP works by way of electrical, mechanical, drainage, and water supply works are now complete.
              • 38% of all carpentry & joinery works are complete 32% of the aluminium and glass works for the windows and doors is complete.
              • 27% of floor tiling is complete.

              Building 11

              • 100% of the sub-structure is complete.
              • 100% of super-structure is complete.
              • 100% of all block work is complete.
              • 67% of all plastering work is complete.
              • 50% of wall tiling is complete.
              • 42 % of all MEP works by way of electrical, mechanical, drainage, and water supply works are now complete.

              PHASE THREE:

              Building 12

              • The building foundations were cast on 29th September.
              • The contractor is finalising the steel and shutter works in preparation for casting the structural columns.

              September 2010 Report

              PHASE ONE:

              • Phase one buildings have been handed over.
              • Minor snags are being carried out by the contractor in the areas surrounding the buildings.
              • Approximately 50% of all apartments are now tenanted.

              PHASE TWO:

              Buildings 7,8 & 9 These 3 buildings are progressing in close parallel as follows:

              • 100% of the sub-structure is complete.
              • 100% of super-structure is complete.
              • 100% of all block work is complete.
              • 75% of all plastering work is complete.
              • 25% of all MEP works by way of electrical, mechanical, drainage, and water supply works are now completeTiling works for the walls in building 10 is 97% complete.

              Building 10

              • 100% of the sub-structure is complete.
              • 100% of super-structure is complete.
              • 100% of all block work is complete.
              • 90% of all plastering work is complete.
              • 90% of wall tiling is complete.
              • 68% of aluminium and glass works for the windows and doors is complete.
              • 45% of the interior paintwork is complete.
              • 40 % of all MEP works by way of electrical, mechanical, drainage, and water supply works are now complete.
              • 30% of all carpentry & joinery works are complete
              • 20% of the aluminium and glass works for the windows and doors is complete.
              • 18% of floor tiling is complete.

              Building 11

              • 100% of the sub-structure is complete.
              • 100% of super-structure is complete.
              • 100% of all block work is complete.
              • 50% of all plastering work is complete
              • 45% of wall tiling is complete.
              • 30 % of all MEP works by way of electrical, mechanical, drainage, and water supply works are now complete.

              PHASE THREE:

              Building 12

              • The foundation excavation has been completed.
              • The previous contractors failed to meet their programme timetable and in order to get back on schedule a new main contractor (Azuri Contracting) has been mobilized.

              August 2010 Report

              PHASE ONE:

              • The final de snagging has been completed and the inspection was done by BSBG last week.
              • Final inspection took place on Sunday 1st August and final sign off will occur upon receipt of developer undertaking for balance of remaining snags during the defects liability period.

              PHASE TWO:

              • Tiling works for the walls in building 10 is 97% complete
              • 40% of the flooring is complete in building 10.
              • Tiling works for the walls in building 11 is 70% complete
              • 20% of the flooring is complete in building 11.
              • The block work is completed in buildings 7, 8 & 9.
              • Plaster works is 25 % done in buildings 7, 8 & 9.
                MEP, electrical and fire fighting works are in progress at different stages in each building.

              PHASE THREE:

              • The contractor ICC has now mobilized to site and preparation for final ground works before casting foundations are underway.

              July 2010 Report

              PHASE ONE:

              • The final inspection on the de snagging list for phase one buildings will be carried out in the 1st week of July.

              PHASE TWO:

              • The super structure concrete works for all the buildings are now completed.
              • Block works have been completed in all the buildings.
              • Plaster works:
                - 45% completed in buildings 7&11
                - 60% completed in building 8&9.
                - 100% completed in building 10.
              • Paint works:
                - 40% of the paint works completed in building 10. ����
              • MEP works (electrical, fire fighting, pluming and AC):
                - 30% in building 7, 10&11.
                - 20% in buildings 8&9. ��

              PHASE THREE:

              • The excavation for the foundation has been completed.
              • The contractor has started his mobilization to the site.

              June 2010 Report

              PHASE ONE:

              • UniEstate has confirmed all units will be de-snagged by 15th June.
              • BSBG will commence de-snagging checks on 16th June for all buildings

              PHASE TWO:

              • The super structure concrete works for all the buildings are now completed.
              • Block works in buildings 10 & 11 have been completed.
              • 95% of block work is complete in buildings 8 and 80% in buildings 7 & 9.
              • 70% of the wall's ceramic is completed in building 10 and 30% in building 11.
              • MEP, electrical and fire fighting works are in progress.

              PHASE THREE:

              • Excavation of the site has commenced with contractor mobilization

              May 2010 Report

              PHASE ONE:

              • The final inspection is done by BSBG on 18/04/2010.
              • Any new or outstanding snags from the final inspection have been handed to contractor for their attendance and the expected date for completion of all phase one snags is 15/05/2010.

              PHASE TWO:

              • 100% of super structure has been completed for all buildings (7-11).
              • Block works in buildings 10 & 11 have been completed.
              • 95% of block work is complete in building 8
              • 80% of block work is complete in buildings 7 & 9.
              • 70% of the wall's ceramic is complete in building 10
              • 30% of the wall's ceramic is complete in building 11.
              • MEP, electrical and fire fighting system works are in progress.

              April 2010 Report

              PHASE ONE:

              • All phase 1 buildings snagging has been completed.
              • The final inspection is due on 15th of April, 2010.
              • The excavation for the lake has been completed from building 1 side up to Building 8.
              • The tender for the MEP and civil works related to lake has been floated.

              PHASE TWO:

              • The super structure concrete works for all the buildings are now complete.
              • Block works in Buildings 10 & 11 have been completed.
              • 90% of block work is complete in buildings 8 and 80% in buildings 7 & 9.
              • 60% of the wall's ceramic is completed in building 10 and 30% in building 11.
              • MEP, electrical and firefighting equipment works have started.

              * Please note that the details of construction progress for this development are largely provided to us by the project consultants and contractors. Any reference to future construction milestone dates is in accordance with their reports to us and The First Group are unable to accept responsibility for any errors.