Construction Status

March Report

  • Steel and shuttering work then pouring concrete for vertical elements in the core walls and retaining wall.
  • Scaffolding work for Ground floor slab.
  • Steel work for Ground Floor beams.
  • Casting of the ground floor is expected to be on the 15th of March, 2010.
  • Water proofing work for retaining walls.
  • Basement 3 cleaning.
  • Post Tension drawings have been submitted to DM on 25/02/2010.
  • Interior Designer is working on the final approval of the interior's drawings and samples.