Construction Status
March Report
- Steel and shuttering work then pouring concrete for vertical elements in the core walls and retaining wall.
- Scaffolding work for Ground floor slab.
- Steel work for Ground Floor beams.
- Casting of the ground floor is expected to be on the 15th of March, 2010.
- Water proofing work for retaining walls.
- Basement 3 cleaning.
- Post Tension drawings have been submitted to DM on 25/02/2010.
- Interior Designer is working on the final approval of the interior's drawings and samples.