Construction History
March 2012

February 2012

January 2012

December 2011

November 2011

October 2011

September 2011

August 2011

July 2011
June 2011 Report
- The 26th typical residential roof slab (30th slab) has been casted on 21/06/2011.
- The top out of the building is scheduled to be on 11/8/2011.(Completion of the super structure)
- The Block works are in progress as follows:
100% completed up to level 24
20% completed at level 25. - The plaster works are in progress as follows:
Mezzanine up to and including level 20 100% completed.
Levels 21-24 20% completed. - Painting works in Basement 1 through podium 3 is 100% completed.
- Painting works levels 4 -15:
100% completed; (primer and putty coats). - MEP works (AC, drainage, water pipes, sewerage and firefighting) are in progress up to the 21st residential floor.
- Water proofing works for wet areas: levels 4-12 100% completed.
- Ceramic tiles for bathroom's walls:
Level 7 100% completed.
Levels 8 & 9 35% completed.
May 2011 Report
- 100% of the sub-structure is complete.
- The 23rd slab representing the 27th typical residential floor was cast on 28th May
- The 25th slab representing the 29th typical residential floor is due to be cast on 15th June
- Block works are in progress as follows:
Ground to Level 19: 100% completed
Level 20: 20% completed - Plaster works are in progress as follows:
Basement to Level 12: 100% completed.
Levels 13 – 17: 20% completed - 100% of painting works are completed up to Podium 3
- 100% of primer and putty painting coats are completed up to Level 10
- MEP works (AC, drainage, water pipes, sewerage and fire fighting) are in progress up to the 16th residential floor.
- Water proofing works for wet areas 100% completed up to Level 8
- Ceramic tiling to bathroom walls 100% complete to Level 6 and 50% complete in Levels 7 & 8
April 2011 Report
- 100% of the sub-structure is complete.
- The 23rd floor representing the 19th typical residential roof slab was cast on 24th April
- Block works are in progress as follows:
Ground to Level 17: 100% completed.
Level 18: 30% completed - Plaster works are in progress as follows:
Basement to Level 10: 100% completed.
Level 11: 90% completed
Level 12: 30% completed
Level 13: 10% completed - 100% of painting works are completed up to Podium 3
- 70% of primer and putty painting coat are completed up to Level 8
- MEP works (AC, drainage, water pipes, sewerage and fire fighting) are in progress up to the 14th residential floor.
- Water proofing works for wet areas 100% completed up to Level 6
- Ceramic tiling to bathroom walls 100% complete at Level 4
and 60% complete in Level 5.
March 2011 Report
- 100% of the sub-structure is complete.
- The 19th floor representing the 15th typical residential roof slab will be cast on 24th March.
- Block works are in progress as follows:
Ground to Level 12: 100% completed.
Level 13: 10% completed. - Plaster works are in progress as follows: Basement to Level 7: 100% completed.
Level 8: 50% completed. - 85% of painting works are completed up to Podium 3.
- 70% of primer coat painting works are completed between Levels 4-6:
- MEP works (AC, drainage, water pipes, sewerage and fire fighting) are in progress up to the 11th residential floor.
- The mock-up unit is complete apart from some finishing works to kitchen to be completed imminently.
February 2011 Report
- 100% of the sub-structure is complete.
- The 16th floor representing the 12th typical residential floor slab was cast on 19th February
- Block works are in progress as follows:
Ground-Podium 3: 100% completed
Level 4-9: 100% completed
Level 10: 90% completed
Level 11: 60% completed - Plaster works are in progress as follows:
Basement � Podium 2:100 % completed
Podium 3: 90% completed
Level 4-6: 100% completed
Level 7: 50% completed - 75% of painting works are completed up to Podium 3
- MEP works (AC, drainage, water pipes, sewerage and fire fighting) are in progress up to the 7th residential floor.
January 2011 Report
- 100% of the sub-structure is complete.
- The 9th floor was cast December.
- Block works are in progress as follows:
Ground-Podium 3: 100% completed.
Level 4: 95%
Level 5: 80%
Level 6: 25% - Plaster works are in progress as follows:
Basement 1: 100% completed
Ground Floor: 100%
Mezzanine Floor: 98%
Podium 1&2: 97%
Podium 3: 90%
Level 4: 30%. - Painting works in Basement1 through to podium 2 is 60% completed.
- MEP works (AC, drainage, water pipes, sewerage and firefighting) are in progress up to the 4th residential floor.
December 2010 Report
- 100% of the sub-structure is complete
- The 7th floor will be cast on 8th December.
- Block works are in progress as follows:
- Ground-Podium 2: 100% completed.
- Podium3: 5% completed.
- Level 5: 25% completed.
- Plaster works are in progress as follows:
- B1: 100%
- Ground Floor: 98%.
- Mezzanine Floor: 95%.
- Podium 1&2: 95%.
- Painting works in Basement1 through to Podium 2 is 50% completed.
- MEP works (AC, drainage, water pipes, sewerage and firefighting) are in progress.
November 2010 Report
- 100% of the sub-structure is complete
- The 1st typical residential floor slab (5th slab) was cast on 22/10/2010.
- The 2nd typical residential slab will be cast on 10/11/2010.
- 100% of block work has been completed on the Mezzanine floor
- 95% of block works are complete on the Ground floor
- 80% of block works are completed on the 1st Podium floor
- MEP works are underway up to the 1st podium level.
October 2010 Report
- 100% of the sub-structure is complete
- The 4th and final podium slab was cast on 23rd September.
- The 5th floor slab being the first typical floor is due to be cast on 15/10/2010.
- 100% of the block work is complete in the basement with 50% complete in the ground floor and 10% in the mezzanine floor.
September 2010 Report
- 4th podium slab cast 23rd September 2010.
- 100% of the sub-structure is complete.
- The 3rd podium slab was cast on 1st September.
- The 4th and final podium slab will be cast on 15/09/2010.
- The casting of typical floor slabs will commence immediately thereafter.
August 2010 Report
- The Mezzanine floor was cast in the week ending 23/07/2010.
- The 1st podium slab is due to be cast by 7th August.
- The final building permit based on the revised structural design has been received from Dubai Municipality.
- The renders and the design of the upgraded units, standard units and common areas have been completed by John R Harris and Partners (JRHP).
July 2010 Report
- All the vertical elements for the structure has been cast
- Retaining walls are 100% completed.
- The shuttering and steel work for the Ground floor slab is completed.
- The Ground floor slab was cast on the 30/06/2010
June 2010 Report
- Casting of the raft foundation started at 10am on 27th of May and was completed at 4pm 28th May. A total of 4200 cubic metres of cement was used.
- The shuttering and steel works for the Ground�s floor slab has started; expected to pour the concrete at by 30th June.
- The contract documents have been delivered to us for stamping and signing on 31/5/2010.
- The revised Gross Floor Area has been approved by DSC and application submitted to DM on 1st of June for approval.
- The foundations are 100% complete.
May 2010 Report
- The steel works are in progress in the lift pit area and this is expected to be cast in mid May.
- 100% of the water proof membrane of the Floor and wall has been completed for the foundation levels.
- 100% of the solid block walls on the 1st & 2nd levels of the foundation has been completed
April 2010 Report
- Casting of the P.C.C for the lift pit is complete.
- Two layers of water proofing membrane for the floor and walls of the lift pit area are complete.
- The protection board for the wall and the protection screed for the floor of the lift pit area are complete.
- Casting of the P.C.C for the 1st & 2nd levels on the foundation is completed.
- 40% of the water proof membrane of the (Floor and wall) has been completed for the foundation levels.
- The Pile head treatment is complete.
- 85% of the solid block wall is in progress for the 1st & 2nd levels on the foundation.
- All levelling and compaction works have been completed.
- Casting of the P.C.C for the water tanks is complete.
* Please note that the details of construction progress for this development are largely provided to us by the project consultants and contractors. Any reference to future construction milestone dates is in accordance with their reports to us and The First Group are unable to accept responsibility for any errors.