Construction Status

March Report

  • The 12th floor slab was cast in 1st week of March.
  • The casting of the 13th floor slab is expected on Saturday the 6th of March, 2010.
  • The steel reinforcement for core wall CW-5 from 12th to u/s 13th floor was completed in 1st week of March.
  • The steel reinforcement for the core wall CW-4 from 13th floor to U/s 14th floor was in 1st week of March.
  • The core CW4 from 13th floor to U/s 14th and CW5 from 12th to U/s 13th floor in 1st week of March.
  • The columns from 12th floor to U/s 13th floor were cast in 1st week of March.
  • The core walls CW-1, CW-2 & CW-3 from 13th floor to U/s 14th floor were cast in 1st week of March.
  • Lighting wiring in progress on ground floor common areas.
  • Fire alarm emergency & voice evacuation system cable pulling in progress in common areas at ground floor.
  • 80% of lighting wiring completed in ground floor units.
  • Structured cabling & telephone cable tray fixing completed 80% at 8th floor.
  • Fire alarm emergency & voice evacuation system cable pulling completed 80% at 9th floor.
  • G.I fixing for power & lighting control in progress from 6th to 8th floor.
  • Bus bar riser marking in progress at 8th floor.
  • 10th floor balcony drain in progress.
  • 80% of 9th floor high level drainage completed.
  • 80% of two drainage risers completed.