Construction Status
March Report
- All block works have been completed in all the floors.
- Plastering works are up to the 8th floor.
- All the MEP conduit works are completed up to the 8th floor.
- The tiling works have commenced in 1st, 2nd and 3rd floors.
- The framing of the curtain walls' works are in progress up to the 3rd floor.
* Please note that the details of construction progress for this development are largely provided to us by the project consultants and contractors. Any reference to future construction milestone dates is in accordance with their reports to us and The First Group are unable to accept responsibility for any errors.