TFG Marina Hotel - to be operated as Wyndham Dubai Marina

Dubai Marina

​When it comes to location TFG Marina Hotel, to be operated as Wyndham Dubai Marina upon completion, will take your breath away. Surrounded by the reflective waters of Dubai Marina, the world’s largest man-made marina, this sought after hotel investment development is in great demand, occupies a premium position in the city’s most in demand district.

Within minutes of arriving at this stunning neighborhood, you will have no doubt as to why it has been voted Dubai’s most coveted district for the second year running.* You will also see exactly why we chose this as the location for one of our most prestigious UAE property developments.

Featuring 497 beautifully appointed, turnkey hotel rooms, Wyndham Dubai Marina is destined to become one of ‘New Dubai’s’ most sought after bases for business and leisure. Within days of announcing this project, we received an overwhelming response, and Wyndham Dubai Marina has generated a great deal of excitement and interest amongst UAE property investors. The good news is that we have a few select VIP suites still available for sale. It comes as no surprise, when everything about the development has that air of prosperity, from its fantastic facilities to the wealth of amenities on its doorstep. Take a short stroll to choose from an array of alfresco dining options along the Marina Promenade or spend a lazy afternoon window shopping on the water’s edge. Just a few minutes away from Wyndham Dubai Marina also lies 'The Walk' at Jumeirah Beach, a hugely popular expansive stretch of beachside cafes, restaurants and shops.

We have selected the very best to oversee all management and operations of this UAE property, in the form of the world’s largest hotel company, Wyndham Hotel Group. Our exciting Marina hotel project, which will be named Wyndham Dubai Marina upon completion, marks a debut for the Wyndham brand in the UAE, a factor that makes this an even more lucrative choice for you as a property investor. With a vast portfolio of more than 7,000 hotels, Wyndham Hotel Group’s global gravitas is destined to have an impact on occupancy levels, and most importantly, a knock on effect on investor returns. Our experience shows us that property opportunities like Wyndham Dubai Marina do not stay around for long. We urge you to contact us today to ensure you do not miss out.

* Named Dubai’s most popular property districts for buying and rental by PropertyFinder.ae in 2012 and 2013.

Show more

Facilities

  • Stunning setting in the heart of Dubai’s most popular property district
  • Managed by the world’s largest hotel company, Wyndham Hotel Group
  • Wi-Fi access throughout and state of the art business facilities
  • 497 hotel rooms across 32 levels, furnished and fitted to the highest standards
  • Full hotel services including 24 hour reception, concierge and room service
  • Within easy access of the Dubai Metro network, Sheikh Zayed Road, and the rest of the city
  • Designed and managed to international 4 star hotel standards
  • Exclusive Club House – four storey annex housing luxurious leisure options including a rooftop swimming pool and high tech gymnasium
top
top

Construction Updates

Previous

August 2014

Next

* Please note that the details of construction progress for this development are largely provided to us by the project consultants and contractors. Any reference to future construction milestone dates is in accordance with their reports to us and The First Group are unable to accept responsibility for any errors.

  • The block works have been completed.
  • The plaster works are in progress at the 32nd floor and in the club house building.
  • The ceramic works for the walls are in progress at the 31st &32nd floors.
  • The ceramic works for the floors are in progress up to the 29th floor.
  • The MEP works are in progress in the 31st & 32nd floors.
  • The aluminum and cladding works are in progress at the four elevations of the main building tower.
  • Steak house: The steakhouse restaurant concept design has been approved by the operator; the working drawings are under preparation for the contractor to commence the works at the site.
Previous

July 2014

Next

* Please note that the details of construction progress for this development are largely provided to us by the project consultants and contractors. Any reference to future construction milestone dates is in accordance with their reports to us and The First Group are unable to accept responsibility for any errors.

  • The block works have been completed.
  • The plaster works are in progress at the 32nd floor.
  • The ceramic works for the walls are in progress at the 30th& 31st floors.
  • The ceramic works for the floors are in progress up to the 28th floor.
  • The MEP works are in progress up to the 31st floor.
  • The aluminum and cladding works are in progress at the four elevations of the main building tower.
  • Steak house: The Tapas Bar concept has been changed by the operator to that of a steakhouse restaurant; the drawings for the fit out concept design have been prepared and presented to the operator for his review and final approval.
Previous

June 2014

Next

* Please note that the details of construction progress for this development are largely provided to us by the project consultants and contractors. Any reference to future construction milestone dates is in accordance with their reports to us and The First Group are unable to accept responsibility for any errors.

  • The building super structure has been completed; the last slab (roof slab) was completed on the 19th of Jan 2014.
  • The block works have been completed.
  • The plaster works are in progress at the 32nd floor.
  • The ceramic works for the walls are in progress at the 29th& 30th floors.
  • The ceramic works for the floors are in progress up to the 26th floor.
  • The MEP works are in progress up to the 31st floor.
  • The aluminum and cladding works are in progress at the four elevations of the main building tower.
  • Mock-Up Units: One bed room unit fully furnished will be ready as a mock up on the 9/7/2014.
  • Tapas Bar: The Tapas Bar concept has been changed by the operator to steakhouse restaurant; the detailed drawings for fit out are being prepared.
Previous

January 2013

Next

* Please note that the details of construction progress for this development are largely provided to us by the project consultants and contractors. Any reference to future construction milestone dates is in accordance with their reports to us and The First Group are unable to accept responsibility for any errors.

Previous

February 2013

Next

* Please note that the details of construction progress for this development are largely provided to us by the project consultants and contractors. Any reference to future construction milestone dates is in accordance with their reports to us and The First Group are unable to accept responsibility for any errors.

Previous

March 2013

Next

* Please note that the details of construction progress for this development are largely provided to us by the project consultants and contractors. Any reference to future construction milestone dates is in accordance with their reports to us and The First Group are unable to accept responsibility for any errors.

Previous

April 2013

Next

* Please note that the details of construction progress for this development are largely provided to us by the project consultants and contractors. Any reference to future construction milestone dates is in accordance with their reports to us and The First Group are unable to accept responsibility for any errors.

Previous

May 2013

Next

* Please note that the details of construction progress for this development are largely provided to us by the project consultants and contractors. Any reference to future construction milestone dates is in accordance with their reports to us and The First Group are unable to accept responsibility for any errors.

  • The casting of the lower raft foundation was completed on 11/04/2013
  • The Internal Design team is continuing its work on the internal designs and finishes; we have completed the 'All Day Dining' area and are now working on the Atrium and the Executive Suites presentations
Previous

June 2013

Next

* Please note that the details of construction progress for this development are largely provided to us by the project consultants and contractors. Any reference to future construction milestone dates is in accordance with their reports to us and The First Group are unable to accept responsibility for any errors.

  • The Ground floor slab was cast on 27/5/2013.
  • The first floor slab was cast on 9/6/2013; the second floor slab casting is expected to happen on the 19/6/2013.
  • The ID team has completed the designing of the units’ ceilings and working on the designing of the lobby’s ceiling.
  • Working with Wyndham design team to incorporate their requirements with regard to the business centre and back of house facilities.
Previous

July 2013

Next

* Please note that the details of construction progress for this development are largely provided to us by the project consultants and contractors. Any reference to future construction milestone dates is in accordance with their reports to us and The First Group are unable to accept responsibility for any errors.

  • The 4th floor slab will be cast on 17/7/2013.
  • The ID team and the operator Wyndham has completed the selection of the finishing items such as tiles, sanitary fittings and mixers
  • The ID team working on the designing of the common areas, corridors and the lobby’s ceiling.
  • Working with Wyndham design team to incorporate their requirements with regard to the business centre and back of house facilities.
Previous

August 2013

Next

* Please note that the details of construction progress for this development are largely provided to us by the project consultants and contractors. Any reference to future construction milestone dates is in accordance with their reports to us and The First Group are unable to accept responsibility for any errors.

  • The 7th floor slab will be cast on 15/08/2013.
  • The ID team and the operator Wyndham has completed the selection of the finishing items such as tiles, sanitary fittings and mixers
  • The ID team working on the designing of the common areas, corridors and the lobby’sceiling.
  • Working with Wyndham design team to incorporate their requirements with regard to the business centre and back of house facilities.
Previous

September 2013

Next

* Please note that the details of construction progress for this development are largely provided to us by the project consultants and contractors. Any reference to future construction milestone dates is in accordance with their reports to us and The First Group are unable to accept responsibility for any errors.

  • The cast of the 11th floor slab was done last Saturday. The contractor is completing a slab every 7-8 days.
  • The block works are in progress up to the 5th floor slab.
  • Guestrooms: All drawings from consultant have been reviewed and finalized. This includes ceilings, lighting, data and power, flooring, and furniture elevations.
  • Guestrooms: All hard finishes and fixtures have been specified.
  • Guestrooms: All in-house drawings are now up to date and a furniture layout of all floors is being finalized.
  • Guestrooms: FF&E specifications and shop drawings have been finalized for the initial design. TFG interiors design (ID) team is working with Wyndham to get the design of the furniture finalized.
  • Guestrooms: The design for the elevator lobbies has been done and detail drawings are with contractor
  • Guestrooms: Pool design details from consultant are under review by TFG ID team.
  • Guestrooms: The concept of a Tapas bar is being explored for the 1st floor specialty F&B retail.
  • Guestrooms: The area between the 2 buildings has been carefully designed as an open atrium that will be supported by the F&B from both sides. On one side the Café in the lobby, and on the other the All Day Dining restaurant. This will be a pleasant outdoor space for lounging and eating with the feel of a provincial garden in an urban space and protected from the elements by the use of a retractable roof.
Previous

October 2013

Next

* Please note that the details of construction progress for this development are largely provided to us by the project consultants and contractors. Any reference to future construction milestone dates is in accordance with their reports to us and The First Group are unable to accept responsibility for any errors.

  • The cast of the 16th floor slab was done last week. The contractor is completing a slab every 7-8 days.
  • The block works are in progress up to the 10th floor slab.
  • The MEP works are in progress up to the 6th floor slab.
  • Guestrooms: All drawings from the consultant have been reviewed and finalized. These include ceilings, lighting, data and power, flooring, and furniture elevations.
  • Guestrooms: All hard finishes and fixtures have been specified.
  • Guestrooms: All in-house drawings are now up to date and a furniture layout of all floors is being finalized.
  • Guestrooms: FF&E specifications and shop drawings have been finalized for the initial design. The First Group’s Interiors Design (ID) team is working with Wyndham to finalize the design of the furniture.
  • Guestrooms: The design for the elevator lobbies has been completed and the detailed drawings have been sent to the contractor for execution in due course at a later stage of the project.
  • Guestrooms: Pool design details have been reviewed by TFG’s ID team and sent back to the consultant and contractor for execution.
  • Guestrooms: The concept of a Tapas bar is being explored for the 1st floor specialty F&B retail.
  • Guestrooms: The area between the 2 buildings has been carefully designed as an open atrium that will be supported by the F&B from both sides. On one side the Café in the lobby, and on the other the All Day Dining restaurant. This will be a pleasant outdoor space for lounging and eating with the feel of a provincial garden in an urban space and it will be protected from the elements by the use of a retractable roof.
Previous

November 2013

Next

* Please note that the details of construction progress for this development are largely provided to us by the project consultants and contractors. Any reference to future construction milestone dates is in accordance with their reports to us and The First Group are unable to accept responsibility for any errors.

  • The casting of the 24rd floor slab was completed last Saturday. The contractor is completing a slab every 7-8 days.
  • The block works are in progress up to the 19th floor.
  • The plaster works are in progress up to the 10th floor.
  • The painting works are in progress up to the 4th floor.
  • The MEP works are in progress up to the 7th floor.
  • Design Progress: Guestrooms design reviewed and agreed with the operator Wyndham; renderings are complete.
  • Design Progress: Guestroom design detailing done and issued to contractor (Wardrobes, Power points, Bedroom furniture, Living room elevations)
  • Design Progress: Commercial Kitchen consultancy concluded concept stage. Left to be done are schematics and detailing. Sketches have been reviewed by Wyndham, the architects, and in house interior design team and have been submitted for authorities’ approvals.
  • Design Progress: We are in the process of appointing the Spa Consultants.
  • Design Progress: The Atrium, proposed Tapas Bar and the swimming pool designs have been completed and reviewed with operator
Previous

December 2013

Next

* Please note that the details of construction progress for this development are largely provided to us by the project consultants and contractors. Any reference to future construction milestone dates is in accordance with their reports to us and The First Group are unable to accept responsibility for any errors.

  • The casting of the 29th floor slab was completed on 26th December. The contractor is completing a slab every 7-8 days.
  • The block works are in progress up to the 24th floor.
  • The plaster works are in progress up to the 15th floor.
  • The painting works are in progress up to the 7th floor.
  • The MEP works are in progress up to the 12th floor.
  • Design Progress: Guestrooms design reviewed and agreed with the operator Wyndham; renderings are complete.
  • Design Progress: Guestroom design detailing done and issued to contractor (wardrobes, power points, bedroom furniture, living room elevations)
  • Design Progress: The Interior design team has completed the schematics and the detailed design drawings for the commercial kitchen. The architect has obtained the authorities’ approvals on the same.
  • Design Progress: We are in the process of appointing the Spa Consultants.
  • Design Progress: The Atrium, proposed Tapas Bar and the swimming pool designs have been completed and reviewed with the operator. We are working on producing the detailed design drawings required for the contractor to commence the works at these areas.
Previous

January 2014

Next

* Please note that the details of construction progress for this development are largely provided to us by the project consultants and contractors. Any reference to future construction milestone dates is in accordance with their reports to us and The First Group are unable to accept responsibility for any errors.

  • The building super structure has been completed; the last slab (roof slab) was completed on the 19th of Jan 2014.
  • The block works are in progress at the 26th, 27th& 28th floors.
  • The plaster works are in progress at the 19th, 20th& 21st floors.
  • The walls ceramic works are in progress at the 16th& 17th floors.
  • The painting works are in progress at the 12th& 13th floors.
  • The MEP works are in progress up to the 19th floor.
  • The aluminum and cladding works are in progress at the four elevations of the main building tower.
  • Common Corridors: Corridor design has been approved by operator.
  • Pool & Spa: Pool terrace and bar design is under review with operator.
  • Pool & Spa: TFG ID team is working on the design of the health club and Spa.
  • Public Washrooms: Public washrooms have been designed and are now subject to TFG and operator approval. This includes a different design for the spa bathrooms.
  • Bar: The new Tapas Bar renderings have been done; undergoing review process.
  • Commercial Kitchens: Design concluded and submitted to authorities. Presently we are waiting for the authority approvals.
  • Commercial Kitchens: Guestrooms design reviewed and agreed with the operator Wyndham; renderings are complete.
  • Commercial Kitchens: Guestroom design detailing done and issued to contractor (Wardrobes, Power points, Bedroom furniture, Living room elevations)
Previous

February 2014

Next

* Please note that the details of construction progress for this development are largely provided to us by the project consultants and contractors. Any reference to future construction milestone dates is in accordance with their reports to us and The First Group are unable to accept responsibility for any errors.

  • The building super structure has been completed; the final slab (roof slab) was completed on the 19th of Jan 2014.
  • The block works are in progress on the 30th, 31st & 32nd floors.
  • The plaster works are in progress on the 24th, 25th & 26th floors.
  • The walls ceramic works are in progress on the 21st & 22nd floors.
  • The painting works are in progress on the 16th & 17th floors.
  • The MEP works are in progress up to the 26th floor.
  • The aluminum and cladding works are in progress for all four elevations of the main building tower.
  • Common Corridors: Corridor design has been approved by operator.
  • Pool & Spa: Pool terrace and bar design has been approved by the operator. The detailed drawings are being prepared for the contractor’s execution requirement.
  • Pool & Spa: TFG Interior Design team is working on the design of the health club and Spa.
  • Public Washrooms: The Public washrooms design has been approved by the operator. The detailed drawings are being prepared for the contractor’s execution requirement.
  • Bar: The new Tapas Bar design reviews were made; the design comments are incorporated and the final renderings are in progress.
  • Commercial Kitchens: Design concluded and submitted to authorities. We are waiting for the authority approvals.
  • Commercial Kitchens: Guestrooms design reviewed and agreed with the operator Wyndham; renderings are complete.
  • Commercial Kitchens: Guestroom design detailing done and issued to contractor (Wardrobes, Power points, Bedroom furniture, Living room elevations)
Previous

March 2014

Next

* Please note that the details of construction progress for this development are largely provided to us by the project consultants and contractors. Any reference to future construction milestone dates is in accordance with their reports to us and The First Group are unable to accept responsibility for any errors.

  • The building super structure has been completed; the final slab (roof slab) was completed on the 19th of Jan 2014.
  • The block works have been completed.
  • The plaster works have been completed up to the 28th & 29th floors.
  • The walls ceramic have been completed up to the 24th floor.
  • The painting works have been completed up to the 19th floor.
  • The MEP works are in progress up to the 29th floor.
  • The aluminum and cladding works are in progress for the four elevations of the main building tower.
  • Common Corridors: Corridor design has been approved by operator.
  • Common Corridors: Lifts Panels mock-up is under production.
  • Pool & Spa: The concept design of the Spa, Pool terrace and bar has been approved by the operator. Now the TFG Interior Design team is working on the detailed design.
  • Public Washrooms: Public washrooms design has been approved by the operator.
  • Main lobby & Tapas Bar: The concept designs along with the renders are being reviewed by the operator.
  • Commercial Kitchens: Approved drawings have been sent to the appointed consultant in Germany for equipment load and mapping purposes.
Previous

April 2014

Next

* Please note that the details of construction progress for this development are largely provided to us by the project consultants and contractors. Any reference to future construction milestone dates is in accordance with their reports to us and The First Group are unable to accept responsibility for any errors.

Previous

May 2014

Next

* Please note that the details of construction progress for this development are largely provided to us by the project consultants and contractors. Any reference to future construction milestone dates is in accordance with their reports to us and The First Group are unable to accept responsibility for any errors.

  • The building super structure has been completed; the last slab (roof slab) was completed on the 19th of Jan 2014.
  • The block works has been completed.
  • The plaster works are in progress at the 30th, 31st & 32nd floors.
  • The ceramic works for the walls are in progress at the 28th floor.
  • The ceramic works for the floors are in progress up to the 23rd floor.
  • The MEP works are in progress up to the 30th floor.
  • The aluminum and cladding works are in progress at the four elevations of the main building tower.
  • Mock-Up Units: Materials selected and Fit-Out is under way.
  • Mock-Up Units: Corridor ceiling mock-up approved with blue cove lights. Fit-out drawing details have been submitted to Contractor.
  • Mock-Up Units: Interior signage panels have been selected and approved.
  • Mock-Up Units: Service doors supplied have been approved.
  • Pool & Spa: Gym design and adjacent WCs concluded. Fit-out detail drawings have been issued to contractor.
  • Pool & Spa: Spa – Design tweaks done and detailed drawings are in progress for the treatment rooms, the reception and retail areas.
  • Public washrooms’ fit-out details have been submitted to Contractor.
  • Lobby fit-out drawing details have been submitted to Contractor. This includes the Café Lounge and exterior Atrium.
  • The All Day Dining Restaurant fit-out detail drawings have been concluded and sent to Contractor.
  • The Tapas Bar fit-out detail drawings under progress. To be tweaked in terms of FF&E.